B1901476 Fence
Address:
3724 E 61ST AVE
SPOKANE,  WA  99223
Parcel #: 34034.0515
Status: Fees paid and permit issued.
Submitted: 5/30/2019
Approved: 6/11/2019
Issued: 6/11/2019
Closed:
Expires: 12/11/2020
Inspections:
Required: 2
Complete: 1
Total Fees:
$44198
Additional fees may be required
Project: 10' HIGH WIND-SCREEN FENCE ALONG WITH COURT VIEWING AREA FOR EXISTING PICKLEBALL COURT

Public Notice

Contacts
TO PRINT A STATUS REPORT FOR THIS PROJECT, FIRST HAVE YOUR PROJECT NUMBER READY, THEN CLICK ON THE COUNTY LOGO, SCROLL TO THE BOTTOM OF THE SCREEN, CLICK REPORTS, CHOOSE THE 'PROJECT STATUS' REPORT, AND ENTER THE PROJECT NUMBER. (IF THE REPORT DOESN'T DISPLAY, IT IS BECAUSE YOUR 'COMPATIBILITY VIEW' SETTINGS ARE TURNED ON. YOU CAN TURN IT OFF BY CLICKING 'TOOLS' > 'COMPATIBILITY VIEW SETTINGS' > AND UNCHECK ALL BOXES. NOW YOUR REPORT WILL PRINT.)
APPLICANT:
SPOKANE COUNTY PARKS/KRIS KROHN
OWNER:
Spokane County Parks, Recreation, and Golf
ENGINEER:
COFFMAN ENGINEERS/THOMAS ARNOLD

Contractors
OWNER/BUILDER:
OWNER PERFORMING THE WORK
License #: OWNER

Details

Parcels
Parcel Owner Address
34034.0515 SPOKANE COUNT 3724 E 61ST AVE
SPOKANE,  WA 99223

Submittals
Submittal Required Received Accepted
Application Yes 5/30/2019 5/30/2019
Site Plan (landscape, 208 drainage, parking) Yes 5/30/2019 5/30/2019

Approval Steps
Below you will find the status of the project application. Each of these steps need to be completed before the application can be finalized and either a permit issued, or the project can be approved. Please contact us for clarification on any status where the Description includes "Migrated from PLUS". 1) "In Queue" means the application has been received by the County and the review steps have been identified. 2) When one of the steps are "In Review", that means a reviewing agency has received the paperwork and has begun their review. 3) "Revisions Requested" means the agency has identified components of the application that need to be received before they can finalize their review. 4) Once a step has been changed to "Complete", that agency has finished their review and no further action is required on the applicant's part.
Step Status Date
Applicant Signature on Application Complete 6/11/2019
Planning Residential Land Use Review Complete 6/3/2019
Contractor License Verification Complete 6/11/2019
Building Commercial Plan Review Complete 6/10/2019
Project Coordinator Complete 6/11/2019
Public Works Commercial/Drainage Review Not Applicable/Not Required 6/3/2019

Reviews
Start Complete Applicant Response

Fixtures
Fixture Quantity Per Unit Value
Total: $0.00

Valuations
Valuation Quantity Rate Value
Total: $0.00

Fees
Fee Amount
Processing, Fence, Residential $104.16
Planning Residential Land Use Review $123.45
Inspection, Fence $189.37
State Surcharge $25.00
Total : $441.98

Bonds
Type Number Amount Issued Expires Completed

Inspections
The following inspections are commonly requested for a permit of this type.
Completed On
Footings 2/21/2020
Final

Structures
Structure Use Occupancy Type Square Footage
FENCE Buildings and structures of an accessory character, miscellaneous

Conditions
FOR INSPECTIONS CALL THE BUILDING AND PLANNING DEPT AT (509) 477-3675 OR REQUEST AN INSPECTION ONLINE AT WWW.SPOKANECOUNTY.ORG/PERMITS. INSPECTION HOURS ARE 7:30-4:00 MONDAY-THURSDAY, AND 7:30-NOON ON FRIDAY.
DISCLAIMER: THIS BUILDING PERMIT REQUIRES POTABLE WATER AND THE APPLICANT IDENTIFIED A “PERMIT-EXEMPT WELL”, AS DEFINED IN RCW 90.44.050, AS THE PROPOSED WATER SOURCE. UNDER RCW 19.27.097 AND WHATCOM COUNTY V. HIRST, 186 WASH.2D 648 (2016), SPOKANE COUNTY IS REQUIRED TO EVALUATE THE SUFFICIENCY OF AN APPLICANT’S EVIDENCE OF AN ADEQUATE WATER SUPPLY FOR THE INTENDED USE OF THE BUILDING PRIOR TO ISSUANCE OF THE BUILDING PERMIT. WATER RIGHTS IN WASHINGTON STATE ARE SUBJECT TO THE ESTABLISHED RULE: “FIRST IN TIME IS THE FIRST IN RIGHT” AND WATER WITHDRAWAL FROM “PERMIT-EXEMPT WELLS” REMAIN SUBJECT TO SENIOR WATER RIGHTS, INCLUDING MINIMUM INSTREAM FLOW RULES ESTABLISHED BY WASHINGTON STATE DEPARTMENT OF ECOLOGY (WSDOE). SPOKANE COUNTY PRESENTLY HAS TWO WATER RESOURCE INVENTORY AREAS (WRIA) SUBJECT TO ADOPTED “INSTREAM FLOW” RULES, WRIA 55 (SEE, WAC 173-555) AND WRIA 57 (SEE WAC 173-557). ON JANUARY 19, 2018, ENGROSSED SUBSTITUTE SENATE BILL 6091, CHAPTER 1, LAWS OF 2018, WATER AVAILABILITY (ESSB 6091) BECAME EFFECTIVE. ESSB 6091 PROVIDES THAT USE OF AN EXEMPT WELL CONSTRUCTED PRIOR TO THE EFFECTIVE DATE OF THE ACT (JANUARY 19, 2018) IS DEEMED EVIDENCE OF AN ADEQUATE WATER SUPPLY UNDER RCW 19.27.097.ESSB 6091 SECTION 202, APPLIES TO BUILDING PERMITS ASSOCIATED WITH WELLS CONSTRUCTED AFTER JANUARY 19, 2018 IN WRIA 55 AND AUTHORIZES POTENTIAL IMPACTS ON CLOSED WATER BODIES AND POTENTIAL IMPAIRMENT TO INSTREAM FLOW FOR NEW DOMESTIC GROUNDWATER WITHDRAWALS EXEMPT UNDER RCW 90.44.050 THROUGH COMPLIANCE WITH THE ESTABLISHED REQUIREMENTS. NEITHER APPLICATION FOR NOR ISSUANCE OF THIS BUILDING PERMIT BY THE SPOKANE COUNTY BUILDING AND PLANNING DEPARTMENT (DEPARTMENT) GUARANTEE THE EXTENT AND/OR VALIDITY OF APPLICANT’S WATER RIGHTS, NOR PROVIDES PROTECTION AGAINST IMPAIRMENT CLAIMS BROUGHT BY SENIOR WATER USERS OR FUTURE ACTIONS BY THE WSDOE. ALL DETAILS, CONTAINED WITHIN THE APPLICATION AND PERMIT DOCUMENTS OF RECORD SUBMITTED BY THE OWNER/APPLICANT OR THEIR AUTHORIZED REPRESENTATIVE, ARE PRESUMED TRUE AND CORRECT FOR THE PURPOSE OF THE DEPARTMENT’S REVIEW. APPROVALS AND ISSUANCE OF PERMITS BASED ON INACCURATE DOCUMENTATION BY THE OWNER/APPLICANT OR THEIR AUTHORIZED REPRESENTATIVE SHALL NOT BE CONSTRUED TO BE AN APPROVAL OF A VIOLATION OF SPOKANE COUNTY BUILDING CODES, OR THE PROVISIONS OF ANY ORDINANCES OF THE SPOKANE COUNTY ENFORCED BY THE DEPARTMENT AND SHALL NOT BE VALID. APPEALS: WITHIN TWENTY-ONE (21) CALENDAR DAYS FROM THE ISSUANCE OF THE PERMIT, A PARTY WITH STANDING MAY FILE A LAND USE PETITION (LUPA) IN SUPERIOR COURT PURSUANT TO CHAPTER 36.70C RCW.
Erodible soils within parcel
Public Transit Benefit Area
High Risk Drainage Area
Public Transit Benefit Area
High Risk Drainage Area

Required Permits
Type Requirement For Number Status

Notes
Generic Permit Report 6/11/2019

Associations